The Missing Middle of Operations and Maintenance: Who Pays for Year Five?
By Chidi Nwafor
At 3 a.m., the solar-powered dispensary in Munje, a coastal village in Kenya, went dark while a woman was in labour. The nurses used a single mobile phone for light. The panels, inverters and batteries had been installed a few years earlier and had worked for a while. Then the batteries failed and were not replaced. In an account published in April 2026, the World Bank’s energy programme, ESMAP, is blunt about the cause: the technology was not flawed. Operation and maintenance were neglected.
This series has followed capital to the construction site through availability, risk, bankability, structure, access and deployment, and then through revenue, currency, the public counterparty, recycling and data. The Missing Middle of Operations and Maintenance is what comes after the ribbon is cut: the gap between an asset that has been commissioned and one that is still working in year five. Capital finances construction, but until very recently almost nothing financed the long middle of an asset’s life. ESMAP says many solar systems in rural African schools and health centres fail within two to three years, or even a few months. When they do, vaccines spoil, oxygen concentrators stop and patients stop coming at night.
Nigeria’s grid shows the same pattern at a larger scale. According to the regulator’s operational factsheet, as reported in March 2026, installed generation capacity was 13,625 MW, while average available capacity in February was 4,384 MW, roughly 32 percent. One plant, Geregu 1, was available 23 percent of the time, with gas disruptions and deferred maintenance cited. Another, the 500 MW Alaoji 1, contributed no available capacity, and the report gave no cause. The article identified the gap between installed and available capacity, not demand, as the binding constraint. Later factsheets show no real change: available capacity averaged 4,744 MW in October. Capacity that is not available is capital that is not working: each idle megawatt is still an asset on someone’s balance sheet, financed by someone’s money.
Off-grid projects tell the story in miniature. A Daily Trust investigation in 2020 found that the Federal Ministry of Power had budgeted over N3.4 billion between 2013 and 2016 for off-grid solar. Plants at Durumi and Shape in the Federal Capital Territory stopped working in 2016; at one a battery burned, and vandals later stripped the panels. Residents said they were never trained to maintain the systems. The ministry replied that communities were responsible for maintenance since they paid nothing for power. Both positions were plausible. The plants stayed dark. The pattern has not gone away. An internal Rural Electrification Agency assessment, reported in September 2026, found only three of seven first-phase university and hospital solar sites in good or usable condition, with degraded panels, failing batteries and dead inverters.
Deferral is expensive. A World Bank diagnostic estimated that preventive road maintenance in Africa could save $2.6 billion a year in rehabilitation capital spending. A South African roads review found that delaying maintenance by three years raised the eventual cost to six times the preventive cost, and by five years to eighteen times. Roads are not power plants, but the arithmetic of neglect is the same. Spares, skills and a repair budget are cheap beside a rebuilt asset.
Why does this persist? Because commissioning is rewarded and maintenance is not. Capital budgets, disbursement targets and ribbon-cutting all attach to the new asset. Operating budgets are recurring, unglamorous and the first to be cut. Contractors are paid at completion and leave. Assets are handed to communities or utilities with no funding for their upkeep, as at Durumi. And every earlier gap in this series lands on maintenance first. A revenue shortfall means no cash for repairs. A currency mismatch makes imported spares dearer. A counterparty that does not pay leaves maintenance contractors unpaid. And without data on failures, no one learns what breaks.
The remedy is to pay for performance rather than equipment. ESMAP proposes that governments buy electricity as a service under long-term, performance-based contracts with private providers, so that the provider’s revenue stops when a system fails and repair becomes a commercial priority. Performance-based maintenance contracts for roads in Argentina were reported to have saved almost 30 percent in additional rehabilitation spending.
Nigeria has begun to build the institution. On 26 August 2026 the Rural Electrification Agency, with the Ministry of Finance Incorporated and Infracorp, launched the Renewable Asset Management Company, RAMCO, to run publicly financed renewable assets after commissioning: contracting operators, handling metering, billing and collection, and maintaining equipment. The Power Minister promised “measurable performance”. That is the right question asked in the right place. But the company is barely three months old, its first portfolio is still being valued and transferred, and the real test is whether it holds, and spends, enough to replace what wears out.
Four things must hold. A funded budget: a maintenance line, reserve account or tariff component that runs for the life of the asset. A named owner: one party accountable for uptime, not shared between ministry, contractor and community. Capability: trained technicians, available spares and a supply chain that functions. And an incentive: payment that depends on whether the asset works.
Few projects test all four before financial close. And every asset has a replacement clock. Inverters, batteries, turbines and transformers have lives shorter than the loan. Twenty-year debt over a ten-year battery requires a replacement in year ten, which someone must fund, and the financial model should show where the cash comes from.
The limits are real. The evidence for performance contracts in off-grid energy is still thin, and ESMAP presents them as a proposal; the road examples come from another sector. Not every failure is a financing failure. Vandalism, insecurity and poor design play their part. And a performance contract is only as good as the party that pays under it. An availability payment from an insolvent counterparty moves the failure; it does not remove it. Measuring performance also requires data that, as the previous article argued, often does not exist.
Where the argument applies, the responsibilities are clear. Governments should fund lifecycle cost, not just construction cost, and refuse to commission what they cannot afford to keep running. Development finance institutions should finance operations as seriously as construction, and make disbursement conditional on a funded maintenance plan. Lenders should require maintenance reserve accounts and an independent engineer’s review every year. Sponsors should contract operation on availability-based terms. Regulators should publish plant availability, as the Nigerian regulator does, and act on it. And buyers of recycled assets should price the operating record, not the nameplate.
A project can be financeable, priced in the right currency, backed by a creditworthy counterparty and well documented, and still fail in year five because no one is paid to keep it running. That is the Missing Middle of Operations and Maintenance. Across this series I have argued that infrastructure rarely fails for want of capital alone. It fails in the middle: between the capital and the asset, the asset and its payer, the payer and its promise, the promise and the evidence, and the evidence and the daily work of keeping the lights on. Capital builds on the first day. Operations decide everything that follows.
Nwafor is founder and lead strategist at De-Lazuli Consult, an advisory practice focused on energy transition, project finance, DFI engagement and infrastructure investment facilitation. He writes from Abuja. [email protected]+2348036761032